VA · Loudoun County

Loudoun data-center permit site — 22275 LOCKRIDGE RD, STERLING, VA

Parcel-level crosswalk of 7 issued Loudoun LandMARC permits whose description or name explicitly contains “data center.”

Identity aliases06227549300322275 LOCKRIDGE RD, STERLING, VA

IDENTITY BASIS

Why these records
belong together.

Loudoun LandMARC issued-permit rows share parcel PIN 062275493003. Address variants remain visible and are not treated as proof of a single operator or campus owner.

Operator named in sources: Not normalized from the current record.

Identity linkage is not an ownership conclusion. Applicant, operator, developer, landowner and permittee can be different entities.

EVIDENCE LAYERS

One row per
government record.

Each value carries its own stage and source basis. Requested values never become permitted or operational through aggregation.

01 · local electrical permit
permittedagency recorded

Electrical (Commercial): ELECC-2024-063870

Issued · Issued 2025-01-07

Permit typeElectrical (Commercial)permitted · agency recorded
Permit work classLow Voltage - Otherpermitted · agency recorded
County permit descriptionEPMS- 25 LV EPMS SCADA DEVICES INSTALLATION FOR PHASE 10 FOR DATA CENTERpermitted · agency recorded
Government recordELECC-2024-063870
Unique evidence keyva-loudoun-pin-062275493003::local-electrical-permit::ELECC-2024-063870::2025-01-07

An issued local permit authorizes the work described by that permit. It does not establish that work was completed, equipment was installed, a data center became operational, stated value was spent or permitted systems are currently in use.

Open controlling source ↗
02 · local electrical permit
permittedagency recorded

Electrical (Commercial): ELECC-2024-063874

Issued · Issued 2025-01-07

Permit typeElectrical (Commercial)permitted · agency recorded
Permit work classLow Voltage - Otherpermitted · agency recorded
County permit descriptionEPMS- 25 LV EPMS SCADA DEVICES FOR PHASE 11 FOR DATA CENTERpermitted · agency recorded
Government recordELECC-2024-063874
Unique evidence keyva-loudoun-pin-062275493003::local-electrical-permit::ELECC-2024-063874::2025-01-07

An issued local permit authorizes the work described by that permit. It does not establish that work was completed, equipment was installed, a data center became operational, stated value was spent or permitted systems are currently in use.

Open controlling source ↗
03 · local electrical permit
permittedagency recorded

Electrical (Commercial): ELECC-2024-063876

Issued · Issued 2025-01-07

Permit typeElectrical (Commercial)permitted · agency recorded
Permit work classLow Voltage - Otherpermitted · agency recorded
County permit descriptionEPMS- 25 LV EPMS SCADA DEVICES INSTALLATION FOR PHASE 12 FOR DATA CENTERpermitted · agency recorded
Government recordELECC-2024-063876
Unique evidence keyva-loudoun-pin-062275493003::local-electrical-permit::ELECC-2024-063876::2025-01-07

An issued local permit authorizes the work described by that permit. It does not establish that work was completed, equipment was installed, a data center became operational, stated value was spent or permitted systems are currently in use.

Open controlling source ↗
04 · local electrical permit
permittedagency recorded

Electrical (Commercial): ELECC-2024-063880

Issued · Issued 2025-01-07

Permit typeElectrical (Commercial)permitted · agency recorded
Permit work classLow Voltage - Otherpermitted · agency recorded
County permit descriptionEPMS- 25 LV EPMS SCADA DEVICES INSTALLATION FOR PHASE 13 FOR DATA CENTERpermitted · agency recorded
Government recordELECC-2024-063880
Unique evidence keyva-loudoun-pin-062275493003::local-electrical-permit::ELECC-2024-063880::2025-01-07

An issued local permit authorizes the work described by that permit. It does not establish that work was completed, equipment was installed, a data center became operational, stated value was spent or permitted systems are currently in use.

Open controlling source ↗
05 · local electrical permit
permittedagency recorded

Electrical (Commercial): ELECC-2024-063893

Issued · Issued 2025-01-07

Permit typeElectrical (Commercial)permitted · agency recorded
Permit work classLow Voltage - Otherpermitted · agency recorded
County permit descriptionEPMS- 25 LV EPMS SCADA DEVICES INSTALLATION FOR PHASE 14 FOR DATA CENTERpermitted · agency recorded
Government recordELECC-2024-063893
Unique evidence keyva-loudoun-pin-062275493003::local-electrical-permit::ELECC-2024-063893::2025-01-07

An issued local permit authorizes the work described by that permit. It does not establish that work was completed, equipment was installed, a data center became operational, stated value was spent or permitted systems are currently in use.

Open controlling source ↗
06 · local electrical permit
permittedagency recorded

Electrical (Commercial): ELECC-2024-063898

Issued · Issued 2025-01-07

Permit typeElectrical (Commercial)permitted · agency recorded
Permit work classLow Voltage - Otherpermitted · agency recorded
County permit descriptionEPMS- 25 LV EPMS SCADA DEVICES INSTALLTION FOR PHASE 15 FOR DATA CENTERpermitted · agency recorded
Government recordELECC-2024-063898
Unique evidence keyva-loudoun-pin-062275493003::local-electrical-permit::ELECC-2024-063898::2025-01-07

An issued local permit authorizes the work described by that permit. It does not establish that work was completed, equipment was installed, a data center became operational, stated value was spent or permitted systems are currently in use.

Open controlling source ↗
07 · local fire marshal permit
permittedagency recorded

FMO - Moderate/High Hazard: FMOMH-2026-017674

Issued · Issued 2026-04-14

Permit typeFMO - Moderate/High Hazardpermitted · agency recorded
Permit work classHazardous Materialpermitted · agency recorded
County permit descriptionEHS Annual Permit for Data Center - IAD285permitted · agency recorded
Government recordFMOMH-2026-017674
Unique evidence keyva-loudoun-pin-062275493003::local-fire-marshal-permit::FMOMH-2026-017674::2026-04-14

An issued local permit authorizes the work described by that permit. It does not establish that work was completed, equipment was installed, a data center became operational, stated value was spent or permitted systems are currently in use.

Open controlling source ↗