Virginia DEQ public notice identifies the applicant, project number, address, coordinates, site scope and requested aquatic-resource impacts.

Operator named in sources: Microsoft Corporation

Identity linkage is not an ownership conclusion. Applicant, operator, developer, landowner and permittee can be different entities.

EVIDENCE LAYERS

One row per
government record.

Each value carries its own stage and source basis. Requested values never become permitted or operational through aggregation.

01 · wetlands section 404 application
requestedagency recorded applicant proposal

MNZ07 Wellington Section 404 public notice

Individual-permit application; comment period closed August 7, 2026 · Public notice opened July 13, 2026

Project area123 acresrequested · agency recorded applicant proposal
Proposed one-story buildings2 buildingsrequested · agency recorded applicant proposal
Requested permanent intermittent-stream impact955 linear feetrequested · agency recorded applicant proposal
Requested intermittent-stream impact area0.14 acresrequested · agency recorded applicant proposal
Requested palustrine emergent wetland impact1.82 acresrequested · agency recorded applicant proposal
Requested palustrine forested wetland impact0.13 acresrequested · agency recorded applicant proposal
Water infrastructure named in noticeWater storage, domestic and fire-hydrant water, sanitary sewer and industrial wastewaterrequested · agency recorded applicant proposal
Public comment deadline2026-08-07requested · agency recorded
Government record26-088F
Unique evidence keyva-prince-william-mnz07-wellington::wetlands-section-404-application::26-088F::2026-07-13

The notice describes requested authorization and applicant-stated impacts. It is not an issued permit or a measurement of completed impacts.

Open controlling source ↗
Extend this dossierSend another official record using the stable facility ID so it can be reviewed as a new evidence layer.
Submit a source →Download crosswalk →All project dossiers →