County GIS crosswalk for Verizon Manassas 7777 Infantry Ridge, retaining the zoning case, EnerGov ID, mapped acreage and planned development fields.
Identity aliasesBattlefield Business ParkVerizon Manassas 7777 Infantry RidgeREZ1988-0030
Was this useful?
One click helps us see which evidence deserves deeper work.
IDENTITY BASIS
Why these records belong together.
Prince William County's Data Center Campuses layer connects zoning case REZ1988-0030 to EnerGov ID 67ae5cc3-3e5f-439d-aa9f-b079257e7927 and mapped campus polygon OBJECTID 45. Multiple polygons can share a zoning case.
Operator named in sources: Not normalized from the current record.
Identity linkage is not an ownership conclusion. Applicant, operator, developer, landowner and permittee can be different entities.
EVIDENCE LAYERS
One row per government record.
Each value carries its own stage and source basis. Requested values never become permitted or operational through aggregation.
01 · county data center campus gis
installedagency recorded
Verizon Manassas 7777 Infantry Ridge county build-out record
Project status: Completed · Prince William County GIS snapshot retrieved August 6, 2026
County GIS project statusCompletedinstalled · agency recorded
GIS acreage20.326 acresinstalled · agency recorded
Planned gross floor area227,465 square feetproposed · agency recorded
Remaining gross floor area0 square feetproposed · agency recorded
Zoning caseREZ1988-0030installed · agency recorded
EnerGov ID67ae5cc3-3e5f-439d-aa9f-b079257e7927installed · agency recorded
Zoning districtPBDinstalled · agency recorded
Inside Data Center Opportunity ZoneYesinstalled · agency recorded
Extend this dossierSend another official record using the stable facility ID so it can be reviewed as a new evidence layer.