County GIS crosswalk for Amazon Parsons Business Park, retaining the zoning case, EnerGov ID, mapped acreage and planned development fields.
Identity aliasesParson Business ParkAmazon Parsons Business ParkREZ2023-00028
Was this useful?
One click helps us see which evidence deserves deeper work.
IDENTITY BASIS
Why these records belong together.
Prince William County's Data Center Campuses layer connects zoning case REZ2023-00028 to EnerGov ID f202a52f-d21d-48eb-ab3e-8577eaaaff93 and mapped campus polygon OBJECTID 33. Multiple polygons can share a zoning case.
Operator named in sources: Not normalized from the current record.
Identity linkage is not an ownership conclusion. Applicant, operator, developer, landowner and permittee can be different entities.
EVIDENCE LAYERS
One row per government record.
Each value carries its own stage and source basis. Requested values never become permitted or operational through aggregation.
01 · county data center campus gis
proposedagency recorded
Amazon Parsons Business Park county build-out record
Project status: Planned · Prince William County GIS snapshot retrieved August 6, 2026
County GIS project statusPlannedproposed · agency recorded
GIS acreage96.899 acresproposed · agency recorded
Planned gross floor area1,876,409 square feetproposed · agency recorded
Remaining gross floor area1,096,340 square feetproposed · agency recorded
Zoning caseREZ2023-00028proposed · agency recorded
EnerGov IDf202a52f-d21d-48eb-ab3e-8577eaaaff93proposed · agency recorded
Zoning districtPBDproposed · agency recorded
Inside Data Center Opportunity ZoneYesproposed · agency recorded
Extend this dossierSend another official record using the stable facility ID so it can be reviewed as a new evidence layer.