Page-cited permit extraction

Northrop Grumman Systems Corporation

Fairfax Co., Virginia

QA status Machine-extractedRelease dated July 29, 2026

EVIDENCE NOTE

What the public record says

A machine-extracted candidate of equipment groups and permit limits stated in Virginia DEQ permit 73872-1, with one-based PDF page citations. Permitted terms do not establish actual operation or emissions.

Primary sourceVirginia DEQ permit document

Virginia Department of Environmental Quality

Open original source ↗

Summary fields cite p. 1, p. 3.

What this record does not establish

The source confirms the document and its stated fields. This profile does not infer actual emissions, compliance history, operating status, facility capacity or environmental impact where those facts are not established by the cited document.

How to read the status

Issued means the agency granted the permit subject to its conditions. It does not mean every permitted unit is operating, that maximum permitted emissions occur, or that later amendments do not exist.

MACHINE-EXTRACTED CANDIDATE

Equipment and limits,
kept separate from actual use.

These page-cited rows are machine-extracted and still require a second manual review. Verify every reused value against the linked official PDF. Page numbers refer to the one-based position in the linked PDF. Blank values are not zero.

Permitted equipment

1 document-defined equipment groups. Counts and per-unit ratings are transcribed; combined capacity is not calculated.

ReferenceEquipment / modelCount / ratingFuel / controlsStated operating fieldSource
engine generator set1 units2500 kW eachSee operating-scope tablep. 3Machine-extracted from explicit permit prose: : 73872 o is authorized to construct and operate: One 2500 kW engine-generator set located at: 2980 Fairview Park Drive Falls Church, Virginia 22042 in accordance with the Condit

Operating scope

Authorized hours, time windows or an explicit finding that no numeric annual-hour cap was located in the reviewed sections.

ReferenceLimitBasisSource

Permitted emission limits

6 pollutant, unit-group and limit rows. These are permit terms, not measured or actual emissions.

Inspect 6 transcribed limit rows
ReferencePollutantLimitBasis / scopeSource
engine-generator set (Ref. #'s EG-1)NOx as NO248.07 lb/hrhourlyp. 7Machine-extracted from a page line in an older official PDF; literal context: 8. Emission Limits: Engine-generator set - Hourly emissions from the operation of the engine-generator set (Ref. #'s EG-1) shall not exceed the limits specified below: Nitrogen Oxides (as N0 ) 48.07 lbs/hr 2
engine-generator set (Ref. #'s EG-1)NOx as NO26.01 lb/hrhourlyp. 7Machine-extracted from a page line in an older official PDF; literal context: Nitrogen Oxides (as N0 ) 48.07 lbs/hr 2 Carbon Monoxide (CO) 6.01 lbs/hr Compliance with the hourly emission limit may be based on testing, if required by DEQ.
NOx as NO218.52 tpyannualp. 8Machine-extracted from a page line in an older official PDF; literal context: 9. Annual Engine-Generator Emission Limits - Total emissions from both engine-generator sets (Ref. #'s EG-1 and EG-2) combined shall not exceed the limits specified below: Nitrogen Oxides (as N0 ) 18.52 tons/yr 2
NOx as NO23.57 tpyannualp. 8Machine-extracted from a page line in an older official PDF; literal context: Nitrogen Oxides (as N0 ) 18.52 tons/yr 2 Carbon Monoxide (CO) 3.57 tons/yr Compliance with these emission limits shall be determined by calculation methods as stated
NOx as NO248.07 lb/hrhourlyp. 8Machine-extracted from a page line in an older official PDF; literal context: 10. Emissions Calculations - Monthly emissions for each pollutant shall be calculated using the following equation and the appropriate emission factors listed below: NOx = [(Total monthly hours of operation of engine-generator set EG-1 x 48.07 lb/hr) + (Total monthly hours of operation of engine-generator set EG-2 x 26.01 lb/hr)] -=•
CO6.01 lb/hrhourlyp. 8Machine-extracted from a page line in an older official PDF; literal context: (Total monthly hours of operation of engine-generator set EG-2 x 26.01 lb/hr)] -=• 2000 CO = [(Total monthly hours of operation of engine-generator set EG-1 x 6.01 lb/hr) + (Total monthly hours of operation of engine-generator set EG-2 x 8.27 lb/hr)] -=-

DOCUMENT HISTORY

What this document says it changes

permit to construct and operate

No superseded-document date is asserted beyond the cited source wording.

p. 1, p. 3

QA NOTES

Ambiguity stays visible

  • Machine-extracted candidate. Verify every reused value against the cited official PDF page.
  • Prose fallback; verify equipment grouping.
  • Older-PDF text fallback; verify row and unit alignment.