Page-cited permit extraction

SDC Ashburn I - SE Parcel Campus

Loudoun Co., Virginia

QA status Machine-extractedRelease dated July 29, 2026

EVIDENCE NOTE

What the public record says

A machine-extracted candidate of equipment groups and permit limits stated in Virginia DEQ permit 74335-1, with one-based PDF page citations. Permitted terms do not establish actual operation or emissions.

Primary sourceVirginia DEQ permit document

Virginia Department of Environmental Quality

Open original source ↗

Summary fields cite p. 1, p. 3.

What this record does not establish

The source confirms the document and its stated fields. This profile does not infer actual emissions, compliance history, operating status, facility capacity or environmental impact where those facts are not established by the cited document.

How to read the status

Issued means the agency granted the permit subject to its conditions. It does not mean every permitted unit is operating, that maximum permitted emissions occur, or that later amendments do not exist.

MACHINE-EXTRACTED CANDIDATE

Equipment and limits,
kept separate from actual use.

These page-cited rows are machine-extracted and still require a second manual review. Verify every reused value against the linked official PDF. Page numbers refer to the one-based position in the linked PDF. Blank values are not zero.

Permitted equipment

2 document-defined equipment groups. Counts and per-unit ratings are transcribed; combined capacity is not calculated.

ReferenceEquipment / modelCount / ratingFuel / controlsStated operating fieldSource
GEN-A1 through GEN-A32 and GEN-C1 through GEN-C32emergency engine generator setCummins · QSK95-G964 units3500 kW eachdiesel fuel oilselective catalytic reduction (SCR)See operating-scope tablep. 5Machine-extracted from an official document equipment table; column grouping requires second review.
GEN-B1 through GEN-B6 and GEN-D1 through GEN-D6emergency engine generator setCummins · QSK95-G912 units3250 kW eachdiesel fuel oilselective catalytic reduction (SCR)See operating-scope tablep. 5Machine-extracted from an official document equipment table; column grouping requires second review.

Operating scope

Authorized hours, time windows or an explicit finding that no numeric annual-hour cap was located in the reviewed sections.

ReferenceLimitBasisSource
GEN-A1 through GEN-A32, GEN-B1 through GEN-B6, GEN-C1 through GEN-C32, and GEN-D1 through GEN-D648 hours/yearLLC Registration Number: 74335 March 20, 2026 Page 7 9. Operating Hours – Each individual emergency diesel engine gen-set (Ref. Nos. GEN-A1 through GEN-A32, GEN-B1 through GEN-B6, GEN-C1 through GEN-C32, and GEN-D1 through GEN-D6) shall not operate more than 48 hours per year for scheduled maintenance checks and readiness testing (Scheduled MCRT, as provided in Condition 5.c). Each individual emergency diesel engine gen-set (Ref. Nos. GEN-A1 through GEN-A32, GEN-B1 through GEN-B6, GEN-C1 thrMachine-extracted normative operating-hours statement; second review pending.p. 9
GEN-A1 through GEN-A32, GEN-B1 through GEN-B6, GEN-C1 through GEN-C32, and GEN-D1 through GEN-D6500 hours/yearecks and readiness testing (Scheduled MCRT, as provided in Condition 5.c). Each individual emergency diesel engine gen-set (Ref. Nos. GEN-A1 through GEN-A32, GEN-B1 through GEN-B6, GEN-C1 through GEN-C32, and GEN-D1 through GEN-D6) shall not operate more than 500 hours per year for all purposes (as provided in Condition 5) combined. The annual limits for hours of operation shall be calculated monthly as the sum of each consecutive 12-month period. Compliance for the consecutive 12-month periodMachine-extracted normative operating-hours statement; second review pending.p. 9

Permitted emission limits

26 pollutant, unit-group and limit rows. These are permit terms, not measured or actual emissions.

Inspect 26 transcribed limit rows
ReferencePollutantLimitBasis / scopeSource
Ref. Nos. GEN-A1 through GEN-A32 and GEN-C1 through GEN-C32 (3,500 ekW)NOx as NO2controlled8.26 lb/hrhourlyp. 11Machine-extracted from an official permit limit table; header grouping requires second review.
Ref. Nos. GEN-B1 through GEN-B6 and GEN-D1 through GEN-D6 (3,250 ekW)NOx as NO2controlled7.49 lb/hrhourlyp. 11Machine-extracted from an official permit limit table; header grouping requires second review.
Ref. Nos. GEN-A1 through GEN-A32 and GEN-C1 through GEN-C32 (3,500 ekW)NOx as NO2uncontrolled97.21 lb/hrhourlyp. 11Machine-extracted from an official permit limit table; header grouping requires second review.
Ref. Nos. GEN-B1 through GEN-B6 and GEN-D1 through GEN-D6 (3,250 ekW)NOx as NO2uncontrolled82.32 lb/hrhourlyp. 11Machine-extracted from an official permit limit table; header grouping requires second review.
Ref. Nos. GEN-A1 through GEN-A32 and GEN-C1 through GEN-C32 (3,500 ekW)NOx as NO26.68 lb/hrhourlyp. 11Machine-extracted from an official permit limit table; header grouping requires second review.
Ref. Nos. GEN-B1 through GEN-B6 and GEN-D1 through GEN-D6 (3,250 ekW)NOx as NO26.16 lb/hrhourlyp. 11Machine-extracted from an official permit limit table; header grouping requires second review.
Ref. Nos. GEN-A1 through GEN-A32 and GEN-C1 through GEN-C32 (3,500 ekW)VOC1.53 lb/hrhourlyp. 11Machine-extracted from an official permit limit table; header grouping requires second review.
Ref. Nos. GEN-B1 through GEN-B6 and GEN-D1 through GEN-D6 (3,250 ekW)VOC1.61 lb/hrhourlyp. 11Machine-extracted from an official permit limit table; header grouping requires second review.
Ref. Nos. GEN-A1 through GEN-A32 and GEN-C1 through GEN-C32 (3,500 ekW)PM1.04 lb/hrhourlyp. 11Machine-extracted from an official permit limit table; header grouping requires second review.
Ref. Nos. GEN-B1 through GEN-B6 and GEN-D1 through GEN-D6 (3,250 ekW)PM1.19 lb/hrhourlyp. 11Machine-extracted from an official permit limit table; header grouping requires second review.
Ref. Nos. GEN-A1 through GEN-A32 and GEN-C1 through GEN-C32 (3,500 ekW)PM101.04 lb/hrhourlyp. 11Machine-extracted from an official permit limit table; header grouping requires second review.
Ref. Nos. GEN-B1 through GEN-B6 and GEN-D1 through GEN-D6 (3,250 ekW)PM101.19 lb/hrhourlyp. 11Machine-extracted from an official permit limit table; header grouping requires second review.
Ref. Nos. GEN-A1 through GEN-A32 and GEN-C1 through GEN-C32 (3,500 ekW)PM2.51.04 lb/hrhourlyp. 11Machine-extracted from an official permit limit table; header grouping requires second review.
Ref. Nos. GEN-B1 through GEN-B6 and GEN-D1 through GEN-D6 (3,250 ekW)PM2.51.19 lb/hrhourlyp. 11Machine-extracted from an official permit limit table; header grouping requires second review.
All Units Controlled by SCRNOx as NO2controlled19.28 tpyannualcombinedp. 12Machine-extracted from an official permit limit table; header grouping requires second review.
All Units Uncontrolled by SCRNOx as NO2uncontrolled75.61 tpyannualcombinedp. 12Machine-extracted from an official permit limit table; header grouping requires second review.
All Units Controlled by SCRNOx as NO2controlled45.76 tpyannualcombinedp. 12Machine-extracted from an official permit limit table; header grouping requires second review.
All Units Uncontrolled by SCRNOx as NO2uncontrolled15.25 tpyannualcombinedp. 12Machine-extracted from an official permit limit table; header grouping requires second review.
All Units Controlled by SCRVOCcontrolled17.00 tpyannualcombinedp. 12Machine-extracted from an official permit limit table; header grouping requires second review.
All Units Uncontrolled by SCRVOCuncontrolled5.67 tpyannualcombinedp. 12Machine-extracted from an official permit limit table; header grouping requires second review.
All Units Controlled by SCRPMcontrolled6.43 tpyannualcombinedp. 12Machine-extracted from an official permit limit table; header grouping requires second review.
All Units Uncontrolled by SCRPMuncontrolled2.14 tpyannualcombinedp. 12Machine-extracted from an official permit limit table; header grouping requires second review.
All Units Controlled by SCRPM10controlled6.43 tpyannualcombinedp. 12Machine-extracted from an official permit limit table; header grouping requires second review.
All Units Uncontrolled by SCRPM10uncontrolled2.14 tpyannualcombinedp. 12Machine-extracted from an official permit limit table; header grouping requires second review.
All Units Controlled by SCRPM2.5controlled6.43 tpyannualcombinedp. 12Machine-extracted from an official permit limit table; header grouping requires second review.
All Units Uncontrolled by SCRPM2.5uncontrolled2.14 tpyannualcombinedp. 12Machine-extracted from an official permit limit table; header grouping requires second review.

DOCUMENT HISTORY

What this document says it changes

permit to construct and operate

No superseded-document date is asserted beyond the cited source wording.

p. 1, p. 3

QA NOTES

Ambiguity stays visible

  • Machine-extracted candidate. Verify every reused value against the cited official PDF page.
  • Verify table column grouping and any alternative models.
  • Confirm whether the limit is per unit, combined, or limited to testing/maintenance.
  • Confirm multi-row and merged-column header association.
← Return to evidence index