Page-cited permit extraction

Vantage Data Center VA3 LLC

Loudoun Co., Virginia

QA status Machine-extractedRelease dated July 29, 2026

EVIDENCE NOTE

What the public record says

A machine-extracted candidate of equipment groups and permit limits stated in Virginia DEQ permit 74284-2, with one-based PDF page citations. Permitted terms do not establish actual operation or emissions.

Primary sourceVirginia DEQ permit document

Virginia Department of Environmental Quality

Open original source ↗

Summary fields cite p. 1, p. 3.

What this record does not establish

The source confirms the document and its stated fields. This profile does not infer actual emissions, compliance history, operating status, facility capacity or environmental impact where those facts are not established by the cited document.

How to read the status

Issued means the agency granted the permit subject to its conditions. It does not mean every permitted unit is operating, that maximum permitted emissions occur, or that later amendments do not exist.

MACHINE-EXTRACTED CANDIDATE

Equipment and limits,
kept separate from actual use.

These page-cited rows are machine-extracted and still require a second manual review. Verify every reused value against the linked official PDF. Page numbers refer to the one-based position in the linked PDF. Blank values are not zero.

Permitted equipment

2 document-defined equipment groups. Counts and per-unit ratings are transcribed; combined capacity is not calculated.

ReferenceEquipment / modelCount / ratingFuel / controlsStated operating fieldSource
GEN-1 through GEN-60non-emergency engine generator setVolvo · Penta TWD1673 GE60 units625 or 560 kW eachdiesel fuel oilselective catalytic reduction (SCR)See operating-scope tablep. 5Machine-extracted from an official document equipment table; column grouping requires second review.
EG-1 through EG-17emergency engine generator setKohler · KD280017 units3010 kW eachdiesel fuel oilSee operating-scope tablep. 5Machine-extracted from an official document equipment table; column grouping requires second review.

Operating scope

Authorized hours, time windows or an explicit finding that no numeric annual-hour cap was located in the reviewed sections.

ReferenceLimitBasisSource
EG-1 through EG-1729 hours/yearVantage Data Centers VA3, LLC Registration Number: 74284 January 5, 2026 Page 8 10. Operating Hours – Emergency Engine Gen-Sets – Each individual emergency diesel engine gen-set (Ref. Nos. EG-1 through EG-17) shall not operate more than 29 hours per year for scheduled maintenance checks and readiness testing (Scheduled MCRT, as provided in Condition 5.c). Each individual emergency diesel engine gen-set (Ref. Nos. EG-1 through EG-17) shall not operate more than 500 hoursMachine-extracted normative operating-hours statement; second review pending.p. 10
EG-1 through EG-17500 hours/year17) shall not operate more than 29 hours per year for scheduled maintenance checks and readiness testing (Scheduled MCRT, as provided in Condition 5.c). Each individual emergency diesel engine gen-set (Ref. Nos. EG-1 through EG-17) shall not operate more than 500 hours per year for all purposes (as provided in Condition 5) combined. The annual limits for hours of operation shall be calculated monthly as the sum of each consecutive 12-month period. Compliance for the consecutive 12-month periodMachine-extracted normative operating-hours statement; second review pending.p. 10
GEN-1 through GEN-6037 hours/yearh to the individual monthly totals for the preceding 11 months. (9VAC5-80-1180) [3/27/2024] 11. Operating Hours – Non-Emergency Engine Gen-Sets – a. The non-emergency diesel engine gen-sets (Ref. Nos. GEN-1 through GEN-60) combined shall not operate more than 37 hours per year when emissions are uncontrolled, calculated daily as the sum of each consecutive 365-day period. b. The non-emergency diesel engine gen-sets (Ref. Nos. GEN-1 through GEN-60) combined shall not operate more than 311,769Machine-extracted normative operating-hours statement; second review pending.p. 10
GEN-1 through GEN-60769 hours/yearhall not operate more than 37 hours per year when emissions are uncontrolled, calculated daily as the sum of each consecutive 365-day period. b. The non-emergency diesel engine gen-sets (Ref. Nos. GEN-1 through GEN-60) combined shall not operate more than 311,769 hours per year when emissions are controlled with SCR, calculated daily as the sum of each consecutive 365-day period. The annual limits for hours of operation shall be calculated daily as the sum of each consecutive 365-day period. CMachine-extracted normative operating-hours statement; second review pending.p. 10

Permitted emission limits

27 pollutant, unit-group and limit rows. These are permit terms, not measured or actual emissions.

Inspect 27 transcribed limit rows
ReferencePollutantLimitBasis / scopeSource
Ref. Nos. EG-1 through EG-17NOx as NO253.09 lb/hrhourlyp. 12Machine-extracted from an official permit limit table; header grouping requires second review.
Ref. Nos. EG-1 through EG-17NOx as NO213.61 lb/hrhourlyp. 12Machine-extracted from an official permit limit table; header grouping requires second review.
Ref. Nos. EG-1 through EG-17VOC2.85 lb/hrhourlyp. 12Machine-extracted from an official permit limit table; header grouping requires second review.
Ref. Nos. EG-1 through EG-17PM100.99 lb/hrhourlyp. 12Machine-extracted from an official permit limit table; header grouping requires second review.
Ref. Nos. EG-1 through EG-17PM2.50.99 lb/hrhourlyp. 12Machine-extracted from an official permit limit table; header grouping requires second review.
Ref. Nos. GEN-1 through GEN-60 Uncontrolled by SCRNOx as NO2uncontrolled9.37 lb/hrhourlyp. 12Machine-extracted from an official permit limit table; header grouping requires second review.
Controlled by SCRNOx as NO2controlled0.50 lb/hrhourlyp. 12Machine-extracted from an official permit limit table; header grouping requires second review.
Ref. Nos. GEN-1 through GEN-60 Uncontrolled by SCRNOx as NO2uncontrolled0.39 lb/hrhourlyp. 12Machine-extracted from an official permit limit table; header grouping requires second review.
Ref. Nos. GEN-1 through GEN-60 Uncontrolled by SCRVOCuncontrolled0.01 lb/hrhourlyp. 12Machine-extracted from an official permit limit table; header grouping requires second review.
Ref. Nos. GEN-1 through GEN-60 Uncontrolled by SCRPM10uncontrolled0.08 lb/hrhourlyp. 12Machine-extracted from an official permit limit table; header grouping requires second review.
Ref. Nos. GEN-1 through GEN-60 Uncontrolled by SCRPM2.5uncontrolled0.08 lb/hrhourlyp. 12Machine-extracted from an official permit limit table; header grouping requires second review.
Ref. Nos. EG-1 through EG-17NOx as NO217.71 tpyannualp. 13Machine-extracted from an official permit limit table; header grouping requires second review.
Ref. Nos. GEN-1 through GEN-60 Uncontrolled by SCRNOx as NO2uncontrolled0.17 tpyannualp. 13Machine-extracted from an official permit limit table; header grouping requires second review.
Controlled by SCRNOx as NO2controlled77.94 tpyannualp. 13Machine-extracted from an official permit limit table; header grouping requires second review.
Ref. Nos. EG-1 through EG-17 and GEN-1 through GEN-60NOx as NO295.82 tpyannualp. 13Machine-extracted from an official permit limit table; header grouping requires second review.
Ref. Nos. EG-1 through EG-17NOx as NO212.38 tpyannualp. 13Machine-extracted from an official permit limit table; header grouping requires second review.
Ref. Nos. GEN-1 through GEN-60 Uncontrolled by SCRNOx as NO2uncontrolled60.80 tpyannualp. 13Machine-extracted from an official permit limit table; header grouping requires second review.
Ref. Nos. EG-1 through EG-17 and GEN-1 through GEN-60NOx as NO273.18 tpyannualp. 13Machine-extracted from an official permit limit table; header grouping requires second review.
Ref. Nos. EG-1 through EG-17VOC4.33 tpyannualp. 13Machine-extracted from an official permit limit table; header grouping requires second review.
Ref. Nos. GEN-1 through GEN-60 Uncontrolled by SCRVOCuncontrolled1.56 tpyannualp. 13Machine-extracted from an official permit limit table; header grouping requires second review.
Ref. Nos. EG-1 through EG-17 and GEN-1 through GEN-60VOC5.89 tpyannualp. 13Machine-extracted from an official permit limit table; header grouping requires second review.
Ref. Nos. EG-1 through EG-17PM100.90 tpyannualp. 13Machine-extracted from an official permit limit table; header grouping requires second review.
Ref. Nos. GEN-1 through GEN-60 Uncontrolled by SCRPM10uncontrolled12.47 tpyannualp. 13Machine-extracted from an official permit limit table; header grouping requires second review.
Ref. Nos. EG-1 through EG-17 and GEN-1 through GEN-60PM1013.37 tpyannualp. 13Machine-extracted from an official permit limit table; header grouping requires second review.
Ref. Nos. EG-1 through EG-17PM2.50.90 tpyannualp. 13Machine-extracted from an official permit limit table; header grouping requires second review.
Ref. Nos. GEN-1 through GEN-60 Uncontrolled by SCRPM2.5uncontrolled12.47 tpyannualp. 13Machine-extracted from an official permit limit table; header grouping requires second review.
Ref. Nos. EG-1 through EG-17 and GEN-1 through GEN-60PM2.513.37 tpyannualp. 13Machine-extracted from an official permit limit table; header grouping requires second review.

DOCUMENT HISTORY

What this document says it changes

amended or superseding permit document

Explicitly supersedes the document dated 2024-03-27.

p. 1, p. 3

QA NOTES

Ambiguity stays visible

  • Machine-extracted candidate. Verify every reused value against the cited official PDF page.
  • Verify table column grouping and any alternative models.
  • Confirm whether the limit is per unit, combined, or limited to testing/maintenance.
  • Confirm multi-row and merged-column header association.