Page-cited permit extraction

Vienna Cloud

Fairfax Co., Virginia

QA status Machine-extractedRelease dated July 29, 2026

EVIDENCE NOTE

What the public record says

A machine-extracted candidate of equipment groups and permit limits stated in Virginia DEQ permit 71804-3, with one-based PDF page citations. Permitted terms do not establish actual operation or emissions.

Primary sourceVirginia DEQ permit document

Virginia Department of Environmental Quality

Open original source ↗

Summary fields cite p. 1, p. 3.

What this record does not establish

The source confirms the document and its stated fields. This profile does not infer actual emissions, compliance history, operating status, facility capacity or environmental impact where those facts are not established by the cited document.

How to read the status

Issued means the agency granted the permit subject to its conditions. It does not mean every permitted unit is operating, that maximum permitted emissions occur, or that later amendments do not exist.

MACHINE-EXTRACTED CANDIDATE

Equipment and limits,
kept separate from actual use.

These page-cited rows are machine-extracted and still require a second manual review. Verify every reused value against the linked official PDF. Page numbers refer to the one-based position in the linked PDF. Blank values are not zero.

Permitted equipment

2 document-defined equipment groups. Counts and per-unit ratings are transcribed; combined capacity is not calculated.

ReferenceEquipment / modelCount / ratingFuel / controlsStated operating fieldSource
emergency engine generator set8 unitsNo reliable per-unit rating transcribeddiesel fuel oilSee operating-scope tablep. 1Machine-extracted from explicit permit prose: Sweet: Attached is a modification to your state operating permit dated January 8, 2004, and amended on May 23, 2005, to add one diesel engine driven emergency generator that had been removed from the last permit, and operate the existing permitted seven diesel engine
emergency engine generator set8 unitsNo reliable per-unit rating transcribeddiesel fuel oilSee operating-scope tablep. 1Machine-extracted from explicit permit prose: This approval to operate eight diesel engine driven emergency electric generators and two boilers shall not relieve Science Applications International Corporation (SAIC) of the resp

Operating scope

Authorized hours, time windows or an explicit finding that no numeric annual-hour cap was located in the reviewed sections.

ReferenceLimitBasisSource
1350 hours/yearScience Applications InWnational Corporation Registration Number: 71804 February 27, 2009 Page 4 OPERATING/EMISSION LIMITATIONS 5. Operating Hours - Cumulatively, diesel engine driven electric generator emission units 1 through 5 shall not operate more than 1350 hours per year, calculated monthly as the sum of each consecutive twelve month period. (9 VAC 5-80-850) 6. Operating Hours - Cumulatively, diesel engine driven electric generator emission units 6 through 8 shall not operate more thanMachine-extracted normative operating-hours statement; second review pending.p. 6

Permitted emission limits

1 pollutant, unit-group and limit rows. These are permit terms, not measured or actual emissions.

Inspect 1 transcribed limit rows
ReferencePollutantLimitBasis / scopeSource
visible emissions30 percent opacityvisiblep. 7Machine-extracted from a page line in an older official PDF; literal context: generator (emission units 1 through 8) shall not exceed twenty percent opacity except during one six-minute period in any one hour in which visible emissions shall not exceed 30 percent opacity as determined by the EPA Method 9 (reference 40 CFR 60, Appendix A). This condition applies at all times except during startup,

DOCUMENT HISTORY

What this document says it changes

amended or superseding permit document

Explicitly supersedes the document dated 2004-01-08.

p. 1, p. 3

QA NOTES

Ambiguity stays visible

  • Machine-extracted candidate. Verify every reused value against the cited official PDF page.
  • Prose fallback; verify equipment grouping.
  • Confirm whether the limit is per unit, combined, or limited to testing/maintenance.
  • Older-PDF text fallback; verify row and unit alignment.