A machine-extracted candidate of equipment groups and permit limits stated in Virginia DEQ permit 73717-3, with one-based PDF page citations. Permitted terms do not establish actual operation or emissions.

Primary sourceVirginia DEQ permit document

Virginia Department of Environmental Quality

Open original source ↗

Summary fields cite p. 3.

What this record does not establish

The source confirms the document and its stated fields. This profile does not infer actual emissions, compliance history, operating status, facility capacity or environmental impact where those facts are not established by the cited document.

How to read the status

Issued means the agency granted the permit subject to its conditions. It does not mean every permitted unit is operating, that maximum permitted emissions occur, or that later amendments do not exist.

MACHINE-EXTRACTED CANDIDATE

Equipment and limits,
kept separate from actual use.

These page-cited rows are machine-extracted and still require a second manual review. Verify every reused value against the linked official PDF. Page numbers refer to the one-based position in the linked PDF. Blank values are not zero.

Permitted equipment

1 document-defined equipment groups. Counts and per-unit ratings are transcribed; combined capacity is not calculated.

ReferenceEquipment / modelCount / ratingFuel / controlsStated operating fieldSource
emergency engine generator setCummins · DQKAN DCC3 units2250 kW eachdiesel fuel oilSee operating-scope tablep. 4Machine-extracted from explicit permit prose: structed: Standby Delegated Equipment Reference No Rated Federal Original Description Permit Date Capaci * Requirements Three (3) Cummins model DQKAN DCC emergency diesel 3,202 bhp EG5, EG6, EG7 engine 2,250 ekW None May 29, gen-sets with 2019 (each unit) engine model QSK60-G#(TBD) (manufactured 2018) Specifications included in the

Operating scope

Authorized hours, time windows or an explicit finding that no numeric annual-hour cap was located in the reviewed sections.

ReferenceLimitBasisSource
500 hours/yearwith the sources electrical system. (9VAC5-80-1180) 8. Operating Hours - The operating hours of the emergency diesel engine gen-sets included in the Equipment List section of this permit are limited to the following: a. No single unit shall operate more than 500 hours per year for all purposes (as provided in Condition 7), calculated monthly as the sum of each consecutive 12-month period; b. No single unit shall operate more than 100 hours per year for maintenance checks and readiness testingMachine-extracted normative operating-hours statement; second review pending.p. 7
100 hours/yearthis permit are limited to the following: a. No single unit shall operate more than 500 hours per year for all purposes (as provided in Condition 7), calculated monthly as the sum of each consecutive 12-month period; b. No single unit shall operate more than 100 hours per year for maintenance checks and readiness testing, calculated monthly as the sum of each consecutive 12-month period; Compliance for each consecutive 12-month period shall be demonstrated monthly by adding the total for theMachine-extracted normative operating-hours statement; second review pending.p. 7

Permitted emission limits

11 pollutant, unit-group and limit rows. These are permit terms, not measured or actual emissions.

Inspect 11 transcribed limit rows
ReferencePollutantLimitBasis / scopeSource
each emergency diesel engine 9 en-set (Ref. Nos.: EG5, EG6, and EG7)NOx as NO231.77 tpyannualp. 8Machine-extracted from a page line in an older official PDF; literal context: Pollutant All Operations Readiness Testing Nitrogen Oxides (as NO2) 31.77tpy 6.35 tpy Carbon Monoxide (CO) 7.41 tpy 1.48 tpy
each emergency diesel engine 9 en-set (Ref. Nos.: EG5, EG6, and EG7)NOx as NO26.35 tpyannualp. 8Machine-extracted from a page line in an older official PDF; literal context: Pollutant All Operations Readiness Testing Nitrogen Oxides (as NO2) 31.77tpy 6.35 tpy Carbon Monoxide (CO) 7.41 tpy 1.48 tpy
each emergency diesel engine 9 en-set (Ref. Nos.: EG5, EG6, and EG7)NOx as NO27.41 tpyannualper unitp. 8Machine-extracted from a page line in an older official PDF; literal context: Readiness Testing Nitrogen Oxides (as NO2) 31.77tpy 6.35 tpy Carbon Monoxide (CO) 7.41 tpy 1.48 tpy Particulate Matter (PM10) 1.14 tpy 0.23 tpy
each emergency diesel engine 9 en-set (Ref. Nos.: EG5, EG6, and EG7)NOx as NO21.48 tpyannualcombinedp. 8Machine-extracted from a page line in an older official PDF; literal context: Readiness Testing Nitrogen Oxides (as NO2) 31.77tpy 6.35 tpy Carbon Monoxide (CO) 7.41 tpy 1.48 tpy Particulate Matter (PM10) 1.14 tpy 0.23 tpy
each emergency diesel engine 9 en-set (Ref. Nos.: EG5, EG6, and EG7)PM101.14 tpyannualper unitp. 8Machine-extracted from a page line in an older official PDF; literal context: Nitrogen Oxides (as NO2) 31.77tpy 6.35 tpy Carbon Monoxide (CO) 7.41 tpy 1.48 tpy Particulate Matter (PM10) 1.14 tpy 0.23 tpy Particulate Matter (PM2.5) 1.14 tpy 0.23 tpy
each emergency diesel engine 9 en-set (Ref. Nos.: EG5, EG6, and EG7)PM100.23 tpyannualcombinedp. 8Machine-extracted from a page line in an older official PDF; literal context: Nitrogen Oxides (as NO2) 31.77tpy 6.35 tpy Carbon Monoxide (CO) 7.41 tpy 1.48 tpy Particulate Matter (PM10) 1.14 tpy 0.23 tpy Particulate Matter (PM2.5) 1.14 tpy 0.23 tpy
each emergency diesel engine 9 en-set (Ref. Nos.: EG5, EG6, and EG7)PM2.51.14 tpyannualper unitp. 8Machine-extracted from a page line in an older official PDF; literal context: Carbon Monoxide (CO) 7.41 tpy 1.48 tpy Particulate Matter (PM10) 1.14 tpy 0.23 tpy Particulate Matter (PM2.5) 1.14 tpy 0.23 tpy
each emergency diesel engine 9 en-set (Ref. Nos.: EG5, EG6, and EG7)PM2.50.23 tpyannualcombinedp. 8Machine-extracted from a page line in an older official PDF; literal context: Carbon Monoxide (CO) 7.41 tpy 1.48 tpy Particulate Matter (PM10) 1.14 tpy 0.23 tpy Particulate Matter (PM2.5) 1.14 tpy 0.23 tpy
visible emissions5 percent opacityvisiblep. 9Machine-extracted from a page line in an older official PDF; literal context: (9VAC5-80-1180 and 9VAC5-50-260) 13. Visible Emission Limit - Visible emissions from each emergency diesel engine gen-set included in the Equipment List section of this permit exhausts shall not exceed 5% opacity except during one 6-minute period in any one hour in which visible emissions shall not
visible emissions10 percent opacityvisiblep. 9Machine-extracted from a page line in an older official PDF; literal context: included in the Equipment List section of this permit exhausts shall not exceed 5% opacity except during one 6-minute period in any one hour in which visible emissions shall not exceed 10% opacity as determined by ERA Method 9 (reference 40 CFR 60, Appendix A). This condition applies at all times except during startup, shutdown and malfunction.
visible emissions20 percent opacityvisiblep. 9Machine-extracted from a page line in an older official PDF; literal context: During startup and shutdown, visible emissions from each emergency diesel engine gen-set shall not exceed 10% opacity except during one 6-minute period in any one hour in which visible emissions shall not exceed 20% opacity as determined by ERA Method 9 (reference 40 CFR 60, Appendix A).

DOCUMENT HISTORY

What this document says it changes

permit to construct and operate

No superseded-document date is asserted beyond the cited source wording.

p. 3

QA NOTES

Ambiguity stays visible

  • Machine-extracted candidate. Verify every reused value against the cited official PDF page.
  • Prose fallback; verify equipment grouping.
  • Confirm whether the limit is per unit, combined, or limited to testing/maintenance.
  • Older-PDF text fallback; verify row and unit alignment.