A machine-extracted candidate of equipment groups and permit limits stated in Virginia DEQ permit 73717-3, with one-based PDF page citations. Permitted terms do not establish actual operation or emissions.
The source confirms the document and its stated fields. This profile does not infer actual emissions, compliance history, operating status, facility capacity or environmental impact where those facts are not established by the cited document.
How to read the status
Issued means the agency granted the permit subject to its conditions. It does not mean every permitted unit is operating, that maximum permitted emissions occur, or that later amendments do not exist.
MACHINE-EXTRACTED CANDIDATE
Equipment and limits, kept separate from actual use.
These page-cited rows are machine-extracted and still require a second manual review. Verify every reused value against the linked official PDF. Page numbers refer to the one-based position in the linked PDF. Blank values are not zero.
Permitted equipment
1 document-defined equipment groups. Counts and per-unit ratings are transcribed; combined capacity is not calculated.
Reference
Equipment / model
Count / rating
Fuel / controls
Stated operating field
Source
emergency engine generator setCummins · DQKAN DCC
3 units2250 kW each
diesel fuel oil—
See operating-scope table—
p. 4 ↗Machine-extracted from explicit permit prose: structed: Standby Delegated Equipment Reference No Rated Federal Original Description Permit Date Capaci * Requirements Three (3) Cummins model DQKAN DCC emergency diesel 3,202 bhp EG5, EG6, EG7 engine 2,250 ekW None May 29, gen-sets with 2019 (each unit) engine model QSK60-G#(TBD) (manufactured 2018) Specifications included in the
Operating scope
Authorized hours, time windows or an explicit finding that no numeric annual-hour cap was located in the reviewed sections.
Reference
Limit
Basis
Source
500 hours/year
with the sources electrical system. (9VAC5-80-1180) 8. Operating Hours - The operating hours of the emergency diesel engine gen-sets included in the Equipment List section of this permit are limited to the following: a. No single unit shall operate more than 500 hours per year for all purposes (as provided in Condition 7), calculated monthly as the sum of each consecutive 12-month period; b. No single unit shall operate more than 100 hours per year for maintenance checks and readiness testingMachine-extracted normative operating-hours statement; second review pending.
this permit are limited to the following: a. No single unit shall operate more than 500 hours per year for all purposes (as provided in Condition 7), calculated monthly as the sum of each consecutive 12-month period; b. No single unit shall operate more than 100 hours per year for maintenance checks and readiness testing, calculated monthly as the sum of each consecutive 12-month period; Compliance for each consecutive 12-month period shall be demonstrated monthly by adding the total for theMachine-extracted normative operating-hours statement; second review pending.
11 pollutant, unit-group and limit rows. These are permit terms, not measured or actual emissions.
Inspect 11 transcribed limit rows
Reference
Pollutant
Limit
Basis / scope
Source
each emergency diesel engine 9 en-set (Ref. Nos.: EG5, EG6, and EG7)
NOx as NO2—
31.77 tpyannual
——
p. 8 ↗Machine-extracted from a page line in an older official PDF; literal context: Pollutant All Operations Readiness Testing Nitrogen Oxides (as NO2) 31.77tpy 6.35 tpy Carbon Monoxide (CO) 7.41 tpy 1.48 tpy
each emergency diesel engine 9 en-set (Ref. Nos.: EG5, EG6, and EG7)
NOx as NO2—
6.35 tpyannual
——
p. 8 ↗Machine-extracted from a page line in an older official PDF; literal context: Pollutant All Operations Readiness Testing Nitrogen Oxides (as NO2) 31.77tpy 6.35 tpy Carbon Monoxide (CO) 7.41 tpy 1.48 tpy
each emergency diesel engine 9 en-set (Ref. Nos.: EG5, EG6, and EG7)
NOx as NO2—
7.41 tpyannual
per unit—
p. 8 ↗Machine-extracted from a page line in an older official PDF; literal context: Readiness Testing Nitrogen Oxides (as NO2) 31.77tpy 6.35 tpy Carbon Monoxide (CO) 7.41 tpy 1.48 tpy Particulate Matter (PM10) 1.14 tpy 0.23 tpy
each emergency diesel engine 9 en-set (Ref. Nos.: EG5, EG6, and EG7)
NOx as NO2—
1.48 tpyannual
combined—
p. 8 ↗Machine-extracted from a page line in an older official PDF; literal context: Readiness Testing Nitrogen Oxides (as NO2) 31.77tpy 6.35 tpy Carbon Monoxide (CO) 7.41 tpy 1.48 tpy Particulate Matter (PM10) 1.14 tpy 0.23 tpy
each emergency diesel engine 9 en-set (Ref. Nos.: EG5, EG6, and EG7)
PM10—
1.14 tpyannual
per unit—
p. 8 ↗Machine-extracted from a page line in an older official PDF; literal context: Nitrogen Oxides (as NO2) 31.77tpy 6.35 tpy Carbon Monoxide (CO) 7.41 tpy 1.48 tpy Particulate Matter (PM10) 1.14 tpy 0.23 tpy Particulate Matter (PM2.5) 1.14 tpy 0.23 tpy
each emergency diesel engine 9 en-set (Ref. Nos.: EG5, EG6, and EG7)
PM10—
0.23 tpyannual
combined—
p. 8 ↗Machine-extracted from a page line in an older official PDF; literal context: Nitrogen Oxides (as NO2) 31.77tpy 6.35 tpy Carbon Monoxide (CO) 7.41 tpy 1.48 tpy Particulate Matter (PM10) 1.14 tpy 0.23 tpy Particulate Matter (PM2.5) 1.14 tpy 0.23 tpy
each emergency diesel engine 9 en-set (Ref. Nos.: EG5, EG6, and EG7)
PM2.5—
1.14 tpyannual
per unit—
p. 8 ↗Machine-extracted from a page line in an older official PDF; literal context: Carbon Monoxide (CO) 7.41 tpy 1.48 tpy Particulate Matter (PM10) 1.14 tpy 0.23 tpy Particulate Matter (PM2.5) 1.14 tpy 0.23 tpy
each emergency diesel engine 9 en-set (Ref. Nos.: EG5, EG6, and EG7)
PM2.5—
0.23 tpyannual
combined—
p. 8 ↗Machine-extracted from a page line in an older official PDF; literal context: Carbon Monoxide (CO) 7.41 tpy 1.48 tpy Particulate Matter (PM10) 1.14 tpy 0.23 tpy Particulate Matter (PM2.5) 1.14 tpy 0.23 tpy
visible emissions—
5 percent opacityvisible
——
p. 9 ↗Machine-extracted from a page line in an older official PDF; literal context: (9VAC5-80-1180 and 9VAC5-50-260) 13. Visible Emission Limit - Visible emissions from each emergency diesel engine gen-set included in the Equipment List section of this permit exhausts shall not exceed 5% opacity except during one 6-minute period in any one hour in which visible emissions shall not
visible emissions—
10 percent opacityvisible
——
p. 9 ↗Machine-extracted from a page line in an older official PDF; literal context: included in the Equipment List section of this permit exhausts shall not exceed 5% opacity except during one 6-minute period in any one hour in which visible emissions shall not exceed 10% opacity as determined by ERA Method 9 (reference 40 CFR 60, Appendix A). This condition applies at all times except during startup, shutdown and malfunction.
visible emissions—
20 percent opacityvisible
——
p. 9 ↗Machine-extracted from a page line in an older official PDF; literal context: During startup and shutdown, visible emissions from each emergency diesel engine gen-set shall not exceed 10% opacity except during one 6-minute period in any one hour in which visible emissions shall not exceed 20% opacity as determined by ERA Method 9 (reference 40 CFR 60, Appendix A).
DOCUMENT HISTORY
What this document says it changes
permit to construct and operate
No superseded-document date is asserted beyond the cited source wording.