Page-cited permit extraction

Microsoft - Gainesville Data Center - MNZ03

Prince William Co., Virginia

QA status Machine-extractedRelease dated July 29, 2026

EVIDENCE NOTE

What the public record says

A machine-extracted candidate of equipment groups and permit limits stated in Virginia DEQ permit 74236-1, with one-based PDF page citations. Permitted terms do not establish actual operation or emissions.

Primary sourceVirginia DEQ permit document

Virginia Department of Environmental Quality

Open original source ↗

Summary fields cite p. 1, p. 3.

What this record does not establish

The source confirms the document and its stated fields. This profile does not infer actual emissions, compliance history, operating status, facility capacity or environmental impact where those facts are not established by the cited document.

How to read the status

Issued means the agency granted the permit subject to its conditions. It does not mean every permitted unit is operating, that maximum permitted emissions occur, or that later amendments do not exist.

MACHINE-EXTRACTED CANDIDATE

Equipment and limits,
kept separate from actual use.

These page-cited rows are machine-extracted and still require a second manual review. Verify every reused value against the linked official PDF. Page numbers refer to the one-based position in the linked PDF. Blank values are not zero.

Permitted equipment

3 document-defined equipment groups. Counts and per-unit ratings are transcribed; combined capacity is not calculated.

ReferenceEquipment / modelCount / ratingFuel / controlsStated operating fieldSource
EG-01emergency engine generator setCaterpillar · C271 units750 kW eachSee operating-scope tablep. 4Machine-extracted from an official document equipment table; column grouping requires second review.
EG-02 through EG-21emergency engine generator setCaterpillar · C175-1620 units3100 kW eachSee operating-scope tablep. 4Machine-extracted from an official document equipment table; column grouping requires second review.
FWP-01and FWP-02fire-pump engineJohn Deere · 4045 Series2 units110 kW eachdiesel fuel oilSee operating-scope tablep. 4Machine-extracted from an official document equipment table; column grouping requires second review.

Operating scope

Authorized hours, time windows or an explicit finding that no numeric annual-hour cap was located in the reviewed sections.

ReferenceLimitBasisSource
EG-01 through EG-2121 hours/yearmaintenance, testing, operational training, and for commissioning during the integration operational period. (9 VAC 5-80-1180) [8/5/2024] 8. Operating Hours – Each individual emergency engine gen-set (Ref. Nos. EG-01 through EG-21) shall not operate more than 21 hours per year for scheduled maintenance checks and readiness testing (Scheduled MCRT, as provided in Condition 6.c.), calculated monthly as the sum of each consecutive 12-month period. Each individual emergency engine gen-set (Ref. NMachine-extracted normative operating-hours statement; second review pending.p. 7
EG-01 through EG-21500 hours/yeard maintenance checks and readiness testing (Scheduled MCRT, as provided in Condition 6.c.), calculated monthly as the sum of each consecutive 12-month period. Each individual emergency engine gen-set (Ref. Nos. EG-01 through EG-21) shall not operate more than 500 hours per year for all purposes (as provided in Condition 6) combined, calculated monthly as the sum of each consecutive 12-month period.Machine-extracted normative operating-hours statement; second review pending.p. 7
FWP-01 and FWP-02500 hours/yearGainesville (MNZ03) Data Center Registration Number: 74236 August 5, 2024 Page 6 Each fire pump (Ref. Nos. FWP-01 and FWP-02) shall not operate more than 500 hours per year for all purposes (as provided in Condition 7) calculated monthly as the sum of each consecutive 12-month period. Compliance for the consecutive 12-month period shall be demonstrated monthly by adding the total for the mMachine-extracted normative operating-hours statement; second review pending.p. 8

Permitted emission limits

31 pollutant, unit-group and limit rows. These are permit terms, not measured or actual emissions.

Inspect 31 transcribed limit rows
ReferencePollutantLimitBasis / scopeSource
Ref. No. EG-01NOx as NO214.74 lb/hrhourlyp. 9Machine-extracted from an official permit limit table; header grouping requires second review.
Ref. No. EG-01NOx as NO257.89 lb/hrhourlyp. 9Machine-extracted from an official permit limit table; header grouping requires second review.
Ref. Nos. FWP- 01 and FWP-02NOx as NO20.93 lb/hrhourlyper unitp. 9Machine-extracted from an official permit limit table; header grouping requires second review.
Ref. No. EG-01NOx as NO21.55 lb/hrhourlyp. 9Machine-extracted from an official permit limit table; header grouping requires second review.
Ref. No. EG-01NOx as NO27.46 lb/hrhourlyp. 9Machine-extracted from an official permit limit table; header grouping requires second review.
Ref. Nos. FWP- 01 and FWP-02NOx as NO20.57 lb/hrhourlyper unitp. 9Machine-extracted from an official permit limit table; header grouping requires second review.
Ref. No. EG-01VOC0.24 lb/hrhourlyp. 9Machine-extracted from an official permit limit table; header grouping requires second review.
Ref. No. EG-01VOC0.85 lb/hrhourlyp. 9Machine-extracted from an official permit limit table; header grouping requires second review.
Ref. Nos. FWP- 01 and FWP-02VOC0.06 lb/hrhourlyper unitp. 9Machine-extracted from an official permit limit table; header grouping requires second review.
Ref. No. EG-01PM100.36 lb/hrhourlyp. 9Machine-extracted from an official permit limit table; header grouping requires second review.
Ref. No. EG-01PM100.39 lb/hrhourlyp. 9Machine-extracted from an official permit limit table; header grouping requires second review.
Ref. Nos. FWP- 01 and FWP-02PM100.06 lb/hrhourlyper unitp. 9Machine-extracted from an official permit limit table; header grouping requires second review.
Ref. No. EG-01PM2.50.36 lb/hrhourlyp. 9Machine-extracted from an official permit limit table; header grouping requires second review.
Ref. No. EG-01PM2.50.39 lb/hrhourlyp. 9Machine-extracted from an official permit limit table; header grouping requires second review.
Ref. Nos. FWP- 01 and FWP-02PM2.50.06 lb/hrhourlyper unitp. 9Machine-extracted from an official permit limit table; header grouping requires second review.
Ref. Nos. EG-01 through EG-21NOx as NO290.04 tpyannualp. 10Machine-extracted from an official permit limit table; header grouping requires second review.
Ref. Nos. FWP-01 and FWP-02NOx as NO20.47 tpyannualp. 10Machine-extracted from an official permit limit table; header grouping requires second review.
Ref. Nos. EG-01 through EG-21NOx as NO234.44 tpyannualp. 10Machine-extracted from an official permit limit table; header grouping requires second review.
Ref. Nos. FWP-01 and FWP-02NOx as NO20.29 tpyannualp. 10Machine-extracted from an official permit limit table; header grouping requires second review.
Ref. Nos. FWP-01 and FWP-02VOC0.03 tpyannualp. 10Machine-extracted from an official permit limit table; header grouping requires second review.
Ref. Nos. EG-01 through EG-21PM102.49 tpyannualp. 10Machine-extracted from an official permit limit table; header grouping requires second review.
Ref. Nos. FWP-01 and FWP-02PM100.03 tpyannualp. 10Machine-extracted from an official permit limit table; header grouping requires second review.
Ref. Nos. EG-01 through EG-21PM2.52.49 tpyannualp. 10Machine-extracted from an official permit limit table; header grouping requires second review.
Ref. Nos. FWP-01 and FWP-02PM2.50.03 tpyannualp. 10Machine-extracted from an official permit limit table; header grouping requires second review.
Total EmissionsNOx as NO290.51 tpyannualp. 10Machine-extracted from an official permit limit table; header grouping requires second review.
Total EmissionsNOx as NO234.73 tpyannualp. 10Machine-extracted from an official permit limit table; header grouping requires second review.
Total EmissionsVOC6.24 tpyannualp. 10Machine-extracted from an official permit limit table; header grouping requires second review.
Total EmissionsPM102.52 tpyannualp. 10Machine-extracted from an official permit limit table; header grouping requires second review.
Total EmissionsPM2.52.52 tpyannualp. 10Machine-extracted from an official permit limit table; header grouping requires second review.
visible emissions10 percent opacityvisiblep. 11Machine-extracted from a page line in an older official PDF; literal context: Page 9 During startup and shutdown, visible emissions from each emergency engine gen-set and fire pump shall not exceed 10% opacity except during one 6-minute period in any one hour in which visible emissions shall not exceed 20% opacity as determined by EPA Method 9
visible emissions20 percent opacityvisiblep. 11Machine-extracted from a page line in an older official PDF; literal context: During startup and shutdown, visible emissions from each emergency engine gen-set and fire pump shall not exceed 10% opacity except during one 6-minute period in any one hour in which visible emissions shall not exceed 20% opacity as determined by EPA Method 9 (reference 40 CFR 60, Appendix A).

DOCUMENT HISTORY

What this document says it changes

permit to construct and operate

No superseded-document date is asserted beyond the cited source wording.

p. 1, p. 3

QA NOTES

Ambiguity stays visible

  • Machine-extracted candidate. Verify every reused value against the cited official PDF page.
  • Verify table column grouping and any alternative models.
  • Confirm whether the limit is per unit, combined, or limited to testing/maintenance.
  • Confirm multi-row and merged-column header association.
  • Older-PDF text fallback; verify row and unit alignment.
← Return to evidence index