NTT Global Data Centers VA10 LLC Prince William County, Virginia
QA status VerifiedRelease dated July 29, 2026
EVIDENCE NOTE
What the public record says A manually verified transcription of equipment groups and permit limits stated in Virginia DEQ permit 74260-2, with one-based PDF page citations. Permitted terms do not establish actual operation or emissions.
What this record does not establish The source confirms the document and its stated fields. This profile does not infer actual emissions, compliance history, operating status, facility capacity or environmental impact where those facts are not established by the cited document.
How to read the status Issued means the agency granted the permit subject to its conditions. It does not mean every permitted unit is operating, that maximum permitted emissions occur, or that later amendments do not exist.
DOCUMENT FIELDS
Permittee named in document NTT Global Data Centers VA10, LLC
Permit number 74260-2
Permit action combined minor NSR permit
Document date April 3, 2026
Facility address VA10 7253 Grove Hill Road; VA11 7251 Grove Hill Road; Gainesville, VA 20155
Application complete 2026-04-03
Explicitly supersedes 2023-11-03
Locality Prince William County
Regional office Northern Regional Office
Regulator Virginia Department of Environmental Quality VERIFIED PERMIT TERMS
Equipment and limits, kept separate from actual use. This is a conservative transcription of reviewed permit sections, not an exhaustive legal digest. Page numbers refer to the one-based position in the linked PDF. Blank values are not zero.
Permitted equipment 4 document-defined equipment groups. Counts and per-unit ratings are transcribed; combined capacity is not calculated.
Reference Equipment / model Count / rating Fuel / controls Stated operating field Source VA11emergency engine gen-set Cummins · C3250D6e 60 units 3250 kW each diesel fuel oil unless noted in permit Miratech ACIS-3 closed-loop SCR See operating-scope table — p. 5 ↗ VA11-Hemergency engine gen-set Cummins · DQGAF 1 units 1500 kW each diesel fuel oil unless noted in permit none See operating-scope table — p. 5 ↗ VA10emergency engine gen-set Cummins · C3250D6e 56 units 3250 kW each diesel fuel oil unless noted in permit none See operating-scope table — p. 6 ↗ VA10-Hemergency engine gen-set Cummins · DQGAF 1 units 1500 kW each diesel fuel oil unless noted in permit none See operating-scope table — p. 6 ↗
Operating scope Authorized hours, time windows or an explicit finding that no numeric annual-hour cap was located in the reviewed sections.
Reference Limit Basis Source VA10, VA10-H, VA11, VA11-H32 hours/year per unit scheduled MCRT Condition 9. p. 10 ↗ VA10, VA10-H, VA11, VA11-H500 hours/year per unit all purposes; rolling consecutive 12 months Condition 9. p. 10 ↗
Permitted emission limits 33 pollutant, unit-group and limit rows. These are permit terms, not measured or actual emissions.
Inspect 33 transcribed limit rows Reference Pollutant Limit Basis / scope Source VA10 / Cummins C3250D6eNOx as NO2 uncontrolled 60.01 lb/hr hourly per unit emergency operation p. 12 ↗ VA10 / Cummins C3250D6eCO uncontrolled 8.29 lb/hr hourly per unit emergency operation p. 12 ↗ VA10 / Cummins C3250D6eVOC uncontrolled 2.64 lb/hr hourly per unit emergency operation p. 12 ↗ VA10 / Cummins C3250D6ePM10 uncontrolled 0.98 lb/hr hourly per unit emergency operation p. 12 ↗ VA10 / Cummins C3250D6ePM2.5 uncontrolled 0.98 lb/hr hourly per unit emergency operation p. 12 ↗ VA10-H / Cummins DQGAFNOx as NO2 uncontrolled 29.37 lb/hr hourly per unit emergency operation p. 12 ↗ VA10-H / Cummins DQGAFCO uncontrolled 7.83 lb/hr hourly per unit emergency operation p. 12 ↗ VA10-H / Cummins DQGAFVOC uncontrolled 1.05 lb/hr hourly per unit emergency operation p. 12 ↗ VA10-H / Cummins DQGAFPM10 uncontrolled 0.46 lb/hr hourly per unit emergency operation p. 12 ↗ VA10-H / Cummins DQGAFPM2.5 uncontrolled 0.46 lb/hr hourly per unit emergency operation p. 12 ↗ VA11 / Cummins C3250D6eNOx as NO2 uncontrolled 60.01 lb/hr hourly per unit emergency operation p. 12 ↗ VA11 / Cummins C3250D6eCO uncontrolled 8.29 lb/hr hourly per unit emergency operation p. 12 ↗ VA11 / Cummins C3250D6eVOC uncontrolled 2.64 lb/hr hourly per unit emergency operation p. 12 ↗ VA11 / Cummins C3250D6ePM10 uncontrolled 0.98 lb/hr hourly per unit emergency operation p. 12 ↗ VA11 / Cummins C3250D6ePM2.5 uncontrolled 0.98 lb/hr hourly per unit emergency operation p. 12 ↗ VA11 / Cummins C3250D6eNOx as NO2 SCR controlled 5.4 lb/hr hourly per unit emergency operation p. 12 ↗ VA11 / Cummins C3250D6eCO SCR controlled 8.29 lb/hr hourly per unit emergency operation p. 12 ↗ VA11 / Cummins C3250D6eVOC SCR controlled 2.64 lb/hr hourly per unit emergency operation p. 12 ↗ VA11 / Cummins C3250D6ePM10 SCR controlled 0.98 lb/hr hourly per unit emergency operation p. 12 ↗ VA11 / Cummins C3250D6ePM2.5 SCR controlled 0.98 lb/hr hourly per unit emergency operation p. 12 ↗ VA11-H / Cummins DQGAFNOx as NO2 uncontrolled 29.37 lb/hr hourly per unit emergency operation p. 12 ↗ VA11-H / Cummins DQGAFCO uncontrolled 7.83 lb/hr hourly per unit emergency operation p. 12 ↗ VA11-H / Cummins DQGAFVOC uncontrolled 1.05 lb/hr hourly per unit emergency operation p. 12 ↗ VA11-H / Cummins DQGAFPM10 uncontrolled 0.46 lb/hr hourly per unit emergency operation p. 12 ↗ VA11-H / Cummins DQGAFPM2.5 uncontrolled 0.46 lb/hr hourly per unit emergency operation p. 12 ↗ VA10,VA10-H,VA11,VA11-HNOx as NO2 facility-wide 94.49 tpy annual all units combined all operations p. 12 ↗ VA10,VA10-H,VA11,VA11-HCO facility-wide 23.7 tpy annual all units combined all operations p. 12 ↗ VA10,VA10-H,VA11,VA11-HVOC facility-wide 12.2 tpy annual all units combined all operations p. 12 ↗ VA10,VA10-H,VA11,VA11-HPM10 facility-wide 5.98 tpy annual all units combined all operations p. 12 ↗ VA10,VA10-H,VA11,VA11-HPM2.5 facility-wide 5.98 tpy annual all units combined all operations p. 12 ↗ VA10,VA10-H,VA11,VA11-Hvisible emissions stated opacity limit 5 percent opacity visible per exhaust/source normal operation p. 13 ↗ VA10,VA10-H,VA11,VA11-Hvisible emissions stated opacity limit 10 percent opacity visible per exhaust/source one six-minute period in any one hour; also startup/shutdown baseline p. 13 ↗ VA10,VA10-H,VA11,VA11-Hvisible emissions stated opacity limit 20 percent opacity visible per exhaust/source one six-minute period in any one hour during startup/shutdown p. 13 ↗
DOCUMENT HISTORY
What this document says it changes combined minor NSR permit Explicitly supersedes the document dated 2023-11-03.
p. 3 ↗ , p. 4 ↗ QA NOTES
Ambiguity stays visible Transcribed from exact official PDF; source page is 1-based PDF position.